Plan Around the Inevitable
Changeovers and scrap are part of cable production – but that doesn’t mean they can’t be controlled. factory.online helps you plan for them, measure them, and reduce their cost.
Changeover Matrices
Cable machines often need significant time to switch between:
Wire sizes
Material grades
Number of strands
Screen/armoring types
How It Works
You define matrix rules:
e.g. Change from copper to steel = 25 min
e.g. Change from 24 to 56 wires = 40 minScheduler adds this time automatically between job orders
Supports different rules for manual vs. automated changeovers
Modes
Additive Mode: Sum all change times
Max Mode: Use only the longest one (for assisted teams)
Fixed Scrap Logic
Some processes always result in predictable waste:
Start-up scrap
Take-up/payout lengths
Equipment configuration meters
Example:
Extrusion: 3m take-up + 5m payout + 50m tuning = 58m scrap per batch
System accounts for this:
When planning material demand
When evaluating actual yield vs. theoretical
Benefits
More accurate material planning
Shorter changeovers through optimization
True performance visibility by job, line, and shift
Stop guessing changeover and scrap. Start controlling them.